STUDY OF CYCLING INFRASTRUCTURE ALTERNATIVES IN YANGUAS Y MIRANDA AND PLAZA DE LOS FUEROS


For the drafting of the preliminary cycling infrastructure project, a study of capacity and traffic matrices in the area was carried out, as well as a microsimulation of the proposed alternatives.

After the studies and the assessment of different factors, a layout in three phases is proposed:

  • Phase 1 Vuelta del Castillo. Layout of the cycling infrastructure behind the bus station. This phase is later developed into a constructive project.
  • Phase 2 Plaza de los Fueros. Elimination of a traffic lane to locate the infrastructure on the road, separated from traffic by a green reservation.
  • Phase 3 Widening Connection. Surface connection through the green area of the Plaza de los Fueros to Avenida de Galicia, with two new pedestrian and cyclist crossings with traffic lights.